05-11-2022 08:43 AM
Hi!
I have a vSZ with v3.4.2 version and I want to upgrade until the v5.2.2. Previusly, I have to upgrade at v3.6.2. I have read the requirement of v5.2.2 and, if I am not wrong, I need 4 node, 18GB RAM per node and 100GB per node. Right now, I have 300 AP into de vSZ and 1000 AP max suported. Also, I have these APs in 3 diferent domains. It is correct?
Thanks!
Solved! Go to Solution.
05-11-2022 10:57 AM
Hi @javier_leal_lil,
Based on your current APs(300) your setup will fall under (1-2 Nodes, 4 Logical processor, 16 GB RAM, 100 GB disk per node.), if you want 1000 APs to be supported in future (1-2 Nodes, 4 Logical processor, 18 GB RAM, 100 GB disk per node.)
You can follow below guides to understand the vSZ requirement based on you current setup and if any future enhancement is planned, it will give you accurate idea for your resource allocation, considering fail over scenarios.
Full Upgrade Guide for 5.2.2
https://support.ruckuswireless.com/documents/3580-smartzone-5-2-2-ga-upgrade-guide
Min requirement Link
05-11-2022 10:57 AM
Hi @javier_leal_lil,
Based on your current APs(300) your setup will fall under (1-2 Nodes, 4 Logical processor, 16 GB RAM, 100 GB disk per node.), if you want 1000 APs to be supported in future (1-2 Nodes, 4 Logical processor, 18 GB RAM, 100 GB disk per node.)
You can follow below guides to understand the vSZ requirement based on you current setup and if any future enhancement is planned, it will give you accurate idea for your resource allocation, considering fail over scenarios.
Full Upgrade Guide for 5.2.2
https://support.ruckuswireless.com/documents/3580-smartzone-5-2-2-ga-upgrade-guide
Min requirement Link
05-12-2022 02:37 AM
Thank you @vijaykuniyal I did not be sure but for your answer I have it clear. Regards.